Project: SF Bay Area: East Bayshore Phase 1A - Interstate 80 Pipeline

Description: Construct 2,500 feet of recycled water transmission main starting from the tertiary treatment plant in Oakland to Emeryville to provide 2,800 AFY of recycled water. water.

Reference Number: 3860-P84-829

Implemented By: Bay Area Clean Water Agencies

Objective: Project will help local public agencies to meet long-term water supply needs, protection of water quality, and augment/restore environmental conditions.

Type: Water Management

Total Cost: $1,364,280.00

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 12/31/2017    Actual Completion: 5/31/2015

Associated Counties: Alameda, Contra Costa, Marin, Napa, San Francisco, San Mateo, Santa Clara, Solano, Sonoma

Located In Disadvantaged Community: Yes

Contribution SourcesContribution DateContribution Amount
  $1,364,280.00
Local Contribution11/21/2011$623,280.00
Prop. 84, Integrated Regional Water Management11/21/2011$741,000.00


Project MetricMetric TopicQuantityUnit
Water ManagementConveyance  
Water ManagementWater Use Efficiency - Recycling  

Location